London Multi-floor strip-out & CAT B fit-out Principal Contractor

20 St Andrew Street, London

Lower Ground · Ground Floor · Level 3 — 2022–2025

Three floors. Three programmes. Two clients. Between 2022 and 2025 Caecus Group worked the full vertical stack at St Andrews House — basement cycle store, ground-floor reset, Level 3 reinstatement.

Three floors. Three programmes. Two clients. What follows is a vertical climb up St Andrews House — a commercial block off Holborn — chronologically through three programmes Caecus delivered between 2022 and 2025. Each is its own story; the building is the through-line.

Lower Ground · 2022

Strip-out & cycle store

Client
CBRE Limited
Role
Principal Contractor
Duration
4 weeks
Value
£120,000

The first programme. Caecus took the lower-ground floor back to a CAT A office shell — partitions and ceilings down, walls made-good and painted, services capped and re-routed — and dropped in a secure cycle store with channel drainage to the perimeter. Service-sensitive: the package sat alongside the building's main intake and the lift pit.

  1. plant-room corridor — bare brick to white walls and resin floor — Existing
    Existing
    plant-room corridor — bare brick to white walls and resin floor — Completed
    Completed

    plant-room corridor — bare brick to white walls and resin floor

  2. cycle-store entry — make-good and channel drainage — Existing
    Existing
    cycle-store entry — make-good and channel drainage — Completed
    Completed

    cycle-store entry — make-good and channel drainage

  3. service riser cluster — exposed slab to clean white — Existing
    Existing
    service riser cluster — exposed slab to clean white — Completed
    Completed

    service riser cluster — exposed slab to clean white

  4. cycle-bay west wall — paint, line marker, channel — Existing
    Existing
    cycle-bay west wall — paint, line marker, channel — Completed
    Completed

    cycle-bay west wall — paint, line marker, channel

Ground Floor · 2024

CAT A reset

Client
CBRE Limited
Role
Principal Contractor
Duration
4 weeks
Value
£150,000

Two years on, CBRE called us back for the ground floor. Full strip-out across the office/retail unit, lift-lobby approach and reception column line — partitions and ceilings down, services capped, demise lines reinstated, made-good and painted. Sequenced with the Lower Ground works to share a single delivery loading point and keep the building running.

  1. reception column line — concrete made-good, painted white — Existing
    Existing
    reception column line — concrete made-good, painted white — Completed
    Completed

    reception column line — concrete made-good, painted white

  2. open floor plate — exposed services to clean ceiling grid — Existing
    Existing
    open floor plate — exposed services to clean ceiling grid — Completed
    Completed

    open floor plate — exposed services to clean ceiling grid

  3. rear unit — bare blockwork to painted demise — Existing
    Existing
    rear unit — bare blockwork to painted demise — Completed
    Completed

    rear unit — bare blockwork to painted demise

  4. service riser opening — capped and made-good — Existing
    Existing
    service riser opening — capped and made-good — Completed
    Completed

    service riser opening — capped and made-good

  5. stair-core landing — handover-ready — Existing
    Existing
    stair-core landing — handover-ready — Completed
    Completed

    stair-core landing — handover-ready

  6. lift-lobby approach — finished demise — Existing
    Existing
    lift-lobby approach — finished demise — Completed
    Completed

    lift-lobby approach — finished demise

Level 3 · 2025

CAT B → CAT A reinstatement

Client
Cushman & Wakefield UK Ltd
Role
Principal Contractor
Duration
12 weeks
Value
£420,000

The largest programme of the three, and a different client. Caecus stripped the existing CAT B fit-out back to slab — partitions, ceilings, services, raised floor — and reinstated the floorplate to a market-ready CAT A: new metal-frame raised floor, suspended ceiling grid, perimeter trunking, fan-coil reinstatement, fresh finishes, made-good lighting, full BMS commissioning. Twelve weeks from possession to handover, with the M&E re-balance running into the final fortnight.

  1. east open-plan — CAT B partitions stripped to slab, CAT A reinstated — Existing CAT B
    Existing CAT B
    east open-plan — CAT B partitions stripped to slab, CAT A reinstated — Reinstated CAT A
    Reinstated CAT A

    east open-plan — CAT B partitions stripped to slab, CAT A reinstated

  2. atrium walkway — perimeter trunking + new fan-coils — Existing CAT B
    Existing CAT B
    atrium walkway — perimeter trunking + new fan-coils — Reinstated CAT A
    Reinstated CAT A

    atrium walkway — perimeter trunking + new fan-coils

  3. meeting-room corridor — full reinstatement — Existing CAT B
    Existing CAT B
    meeting-room corridor — full reinstatement — Reinstated CAT A
    Reinstated CAT A

    meeting-room corridor — full reinstatement

  4. south elevation — fresh finishes, BMS commissioned — Existing CAT B
    Existing CAT B
    south elevation — fresh finishes, BMS commissioned — Reinstated CAT A
    Reinstated CAT A

    south elevation — fresh finishes, BMS commissioned